February 14, 2003
Mr.
Dennis Keschl
Administrative
Director
Maine
Public Utilities Commission
State
House Station #18
Augusta,
ME 04333-0018
For Conservation
Program Planning – Commission Staff Report on the Potential for Energy
Efficiency in Maine and Recommendations for Conservation Program Funding,
Docket No. 2002-162
Dear
Mr. Keschl:
On February 11, 2003, the Commission Staff issued its Report on the Potential for Energy Efficiency in Maine and Recommendations for Conservation Program Funding (the “Report”) in the above-referenced docket. The Report states that interested persons may provide comments or object to the recommendations or analysis set forth in the Report. The deadline for such comments was set at February 24, 2003.
Central Maine Power Company (“CMP”) respectfully
requests a one-week extension in the comment deadline, so that comments would
be due on March 3, 2003. The reason for
this request is that the original deadline would have given CMP less than two
weeks to comment on this lengthy report.
This time frame is especially short when taking into account the fact
that one of these weeks is a school vacation week when many of the personnel
involved in these issues will not be available. Even for those personnel not on vacation, another day to respond
is lost as a result of the Presidents’ Day holiday. Therefore, good cause exists for granting CMP and other
interested persons a one-week extension within which to file comments on the
Report.
Please contact me at (207) 621-6546 if the
Commission or its Staff has any questions regarding this request for extension.
Sincerely,
Richard P. Hevey
Counsel
cc: Service List
2/19/03 Request granted in part.
Extension granted to February 28, 2003.
James A. Buckley
Presiding Officer